Modernization of generator to meet accessibility goals, Mälarenergi

A generator in need of modernization to meet availability goals

Since 1963, Generator 2 has been an integral part of Mälarenergi's operations. Over time, however, its original rotor and stator windings had deteriorated significantly. Recently, several breakdowns have occurred and the condition of the generator has not reached the desired availability targets of 90%. Therefore, the modernization project aimed to improve the availability of the generator by the year 2020, reduce maintenance costs and increase the safety of the personnel in Unit 2. Without this necessary modernization, significant material and personal damage was at risk.

The project was organized in three main parts:

  1. Rewinding of generators
  2. Turbine measures and assembly works 
  3. New magnetization

The project manager from Sigholm was responsible for planning, structuring, implementing and evaluating the project.

A technical project with many responsibilities

The modernization of the generator constituted a comprehensive technical project in which we utilized the internal expertise of specialists in relevant fields. Through this collaboration, we were able to successfully ensure the project's outcome.

In this project, we have taken overall responsibility for the coordination and communication between the involved organizations and the project team. We have carried out a comprehensive feasibility study and recommended appropriate technical solutions. Our team effectively managed the procurement and contracting of qualified designers and technical experts. We were responsible for the careful planning, management, control and coordination of the design, ensuring that all reviews were carried out correctly according to the client's specifications. This included ensuring that the contractor prepared and complied with the required control, quality, health and safety and environmental plans. We created tender documents in accordance with the Public Procurement Act (LOU) and managed the contract signing process together with the procurement officer for the necessary procurements. In addition, we were responsible for establishing and following up on plans regarding scope of supply, timeframes, budget, resources, quality and health, safety and environment (HSE). "HMS" in Swedish.

Our responsibilities also extended to maintaining continuous relations with contractors and suppliers to ensure the smooth implementation of the modernization process. We took care of contracting and ensuring the execution of inspections, as well as overseeing the training processes and the subsequent handover to operations. Furthermore, we managed the negotiations with the contractors to ensure the success of the project.

  • #projektledning
  • #generator
  • #tillgänglighet
  • #turbin
  • #modernisering

The article was published 18/03 - 2020

Contact us for more information
Isabell Stoor

Projektledare & Vd Sigholm Project

You might also be interested in:


Projektledning av nytt badhus, Västerås stad

Sedan juni 2019 står det nya badhuset, Nya Lögarängsbadet på plats i VästeråsMed erfarenhet och förs

Read article
Nya ackumulatorlösningar för att framtidssäkra höga spetsbelastningar

Projektet involverade utmaningar som krävde noggrann planering och kommunikation för att lösa logistiska och tekniska problem. Genom smidig ...

Read article

We have the ambition to make the world better together

At Sigholm, we believe in developing skills in the long term to build the company together. Through shared reflections, we create a culture of continuous learning.

Career at Sigholm

Latest news

Nov 30, 2023 | News | News & press

Leveraging CSRD to create business value

In early 2024, the requirements for all large companies' sustainability reporting will be tightened, and most energy companies will be directly affected. The EU's Corporate Sustainability Reporting Directive (CSRD) will become Swedish law and will, among other things, give sustainability reporting t

Sep 08, 2023 | News & press | Press release

Sigholm increases its workforce by 24%

Sigholm, a prominent player in the energy and civil engineering sector, announces a 24% growth in personnel by welcoming 12 new colleagues within a month. This strengthens the company's capacity and expertise to meet the growing challenges of the market.

Aug 29, 2023 | News | News & press

Energistrategipodden live at Frihamnsdagarna 2023

On Friday 1 September, we will broadcast the first live podcast of the Energy Strategy Podcast during the Frihamnsdagarna in Gothenburg. During the recording, Niclas Sigholm will interview Per-Anders Gustafsson, CEO of Göteborg Energi for an in-depth interview about future energy solutions and susta

Contact Us

Fill out the form, and we will get back to you, visit one of our offices, or call us at +46(0)21-12 03 10.

By clicking send, you agree to Sigholm's handling of your personal data. Read our personal data policy