Project and construction manager for Fredriksberg preschool, Hemsö

In collaboration with Hemsö, we as project and construction managers have had the honor of being part of the creation of Fredriksberg preschool - an innovative children's paradise in Västerås. The building has two levels and six departments and is not only a place for learning but also a work of art in itself, where form and function go hand in hand to create an optimal environment for children and staff. The design of the preschool has been carefully planned to enable educational activities that are both fun and rewarding. Every detail, from color choice to furniture, has been created with the children's needs in focus.

Video produced by Watermark Media Lab

The planning stage

In a successful project, the planning stage is crucial to ensure that all aspects of the project are well coordinated, quality assured and financially sustainable. This is particularly true in the construction and real estate sector, where the complexity of projects requires accuracy at every stage;

Administrative coordination and digital storage

A key element of the project management's work has been the administrative coordination of design consultants. This has included effective coordination of digital storage via a project database, in accordance with Hemsö's specific CAD requirements. By establishing a centralized and accessible digital storage solution, the project team has been able to ensure that all parties involved have access to timely and accurate information, which is crucial to the success of the project.

The project manager has also been responsible for the coordination of action development, including acting as rapporteur at design meetings, booking meetings, coordinating interim meetings and taking minutes. This extensive coordination effort has ensured that all aspects of the project remain on schedule and that communication between the various stakeholders is clear and effective.

Quality assurance

Quality assurance has been another key component, with a particular focus on meeting the requirements of the Silver level of eco-building. In addition, the project has aligned itself with Hemsö's sustainability guidelines, reflecting a commitment to not only meet current standards but also contribute to a more sustainable future.

Effective project management during the implementation phase

The implementation stage of a project is a critical phase where planning meets reality, and the project manager's ability to navigate through challenges becomes crucial to the success of the project. In this case, the project management of the project has demonstrated effectiveness in managing construction contracts, coordinating with different parties, and ensuring the project's objectives and quality standards.

Construction contracts and tenant adaptations

A fundamental responsibility of the project manager has been to ensure compliance with the established construction contract documents. This involves careful monitoring and control of the correct implementation of all agreed conditions and specifications. The project manager has also taken active responsibility for ensuring that the client's commitments are met and carried out in a satisfactory manner.

The project manager's involvement in the design and document review of the turnkey contractor has been a key component in maintaining the project's quality standards. By leading and recording construction meetings and participating in financial meetings, the project manager has ensured continuous dialogue and effective communication between all parties involved.

The project manager has also managed ÄTA (Alteration and Additional Works), which requires a deep understanding of the project's finances and contracts. The project manager also led and coordinated meetings with tenants to discuss and align tenant-specific requests with the overall contract, requiring a balance between flexibility and the overall project schedule and budget.

Risk management and financial overview

The project manager's role has also included construction management, with a specific focus on assisting the contractor with ongoing construction issues and production controls.

Through a committed and proactive approach, the project manager of this construction project has successfully navigated the challenges encountered during the implementation phase. By combining strong leadership skills with technical expertise and financial insight, the project manager not only ensured that the project objectives were achieved, but also that it was carried out in a cost-effective and qualitatively sustainable manner. This article highlights the importance of a well-structured project management strategy and the best practices that can be applied to ensure success in the implementation phase of construction projects.

The article was published 08/03 - 2024

Not just a building but a concept for well-being and learning

Fredriksberg preschool is not just a building, but a concept that promotes children's well-being and learning. It is a place where architecture, nature and pedagogy intertwine to create a harmonious environment. We are proud to have been a part of this project and look forward to seeing how the preschool will shape and inspire generations of children in the future.

Outdoor environment in the spirit of the forest

The outdoor environment is the crown jewel of the preschool, with a thematic focus on the forest. It is divided into three zones, each designed to promote different qualities and functions that enhance the quality of play and create a sense of security. A 'wild zone' where children encounter the natural world, a 'nature zone' for movement and challenge, and a 'safe zone' focused on the youngest children.

https://www.hemso.se/projekt/forskola-kornknarren/

Contact us for more information

We have the ambition to make the world better together

At Sigholm, we believe in developing skills in the long term to build the company together. Through shared reflections, we create a culture of continuous learning.

Career at Sigholm

Latest news

Oct 30, 2024 | News

Sigholm utses till "Tillväxtraket 2024"

Vi är stolta att meddela att vi blivit tilldelade titeln "Tillväxtraket 2024". Sigholm är ett av fåtal bolag som har vuxit mer än 30 procent och tilldelas därmed titeln “Tillväxtraket 2024” både på medarbetarsidan samt omsättningssidan. Vi är oerhört stolta över att bli utsedda till årets tillv

Oct 11, 2024 | News

Vinnare av Stora Näringslivspriset 2024

Vi är glada att meddela att vi, torsdagen den 10 oktober, mottog Stora Näringslivspriset som är instiftat av Handelskammaren Mälardalen.

Sep 27, 2024 | Data analysis | Digitisation | Energy calculations | News | Produktionsplanering

Årsoptimering av energisystem

Under första halvan av 2024 har vi, med vårt optimerings- och uppföljningsverktyg Aurora by Sigholm, framgångsrikt levererat årsoptimeringsprojekt för kraftvärmeproducenter.

Contact Us

Fill out the form, and we will get back to you, visit one of our offices, or call us at +46(0)21-12 03 10.

By clicking send, you agree to Sigholm's handling of your personal data. Read our personal data policy